microsoft-project-training - project
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft-project-training - Project

microsoft-project-training - Project

resolvedResolved · Low Priority · Version Standard

replyReply Wed 23 Jan 2008, 16:50Delegate Natalie said...

Natalie has attended:
Project Introduction course

Project

How many years can you include in a project sheet?

For upcoming training course dates see: Pricing & availability

replyReply Mon 4 Feb 2008, 13:32Trainer Stephen said...

RE: Project

Hi natalie

Thank you for your question

The answer to this is you can include any number of years in your project. There is no limitation on the length of the timeline.

If however your project is of a considerable length then it would be wise to create different views of the GANNT chart, easch showing a different zoom level and timescale. This will help you manage things more easily.

Regards

Stephen

 

Ms project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.