Hints and tips home » MS Project hints and tips » Inserting Task Durations Quickly
Inserting Task Durations Quickly
When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.
Added by Martin on 10th October 2011