Hints and tips home » MS Project hints and tips » Typing Links Between Tasks
Typing Links Between Tasks
In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.
Added by Martin on 10th October 2011