How to get RAG status column

resolvedResolved · Medium Priority · Version 2010

Mary has attended:
Project Intermediate course

How to get RAG status column

RAG status very useful indicator. How to add this

RE: How to get RAG status column

Hi Mary,
Thank you for using the forum to ask a question.

To achieve the RAG status you will need to create custom indicators using a custom field.

Here's an article on how to create the indicators so you can start testing that now.

https://support.office.com/en-gb/article/Add-indicators-09ee6a60-e171-431a-8e1d-58adc2a317cf

We cover this topic on the Advanced Project course if you'd like different indicators for RAG status.


Kind regards

Richard Bailey
Microsoft Certified Trainer

Best STL - https://www.stl-training.co.uk
98%+ recommend us

London's leader with UK wide delivery in Microsoft Office training and management training to global brands, FTSE 100, SME's and the public sector


 