PROJECT FEILD

resolvedResolved · Low Priority · Version 2007

replyReply Mon 2 Jun 2008, 15:50Delegate John said...

John has attended:
Excel Intermediate course
Project Intermediate course

PROJECT FEILD

HOW TO PROJECT % COMPLETE

For upcoming training course dates see: Pricing & availability

replyReply Fri 13 Jun 2008, 12:04Trainer Stephen said...

RE: PROJECT FEILD

Hi John

Thank Your for your question

I assume you would like to see an percentage complete figure for the overall project

If you click on Tool-Options-General and tick the "Show Project Summary task" tick box. This will add a summary task at the top of your Gantt chart whch shows data for the entire project.

You can the add the "% Complete" field in the Gantt chart by right clicking on any column head, selecting insert column and choosing % complete in the "field" combo box of the resulting dialog.

Hope this is useful

Regards

Stephen

 

Please browse our web site to find out more about
2003 microsoft project server and other Microsoft training courses.

Ms project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard