microsoft+project+courses+london - Resource splitting

The UK's most regular instructor-led training courses.
Training information: microsoft+project+courses+london · Project training · Microsoft Project Training
See also · microsoft project training courses · microsoft.project.course · microsoft+project+courses

resolvedResolved · Low Priority · Version Standard

No ranking yet
4 posts
replyReplyFri 4 May 2007, 14:01Delegate Leah said...

Leah has attended:
Excel Intermediate course
Project Intro Intermediate course

Resource splitting

How do I allow two resources to do the same job and have the duration change based on the fact that I now have two resources instead of one? Can you explain effort-driven?

Project Intro Intermediate 2 day course
Version Date Location Places
available
Book Next place rate (£)
Pay by
Card
Pay by
Invoice
2003 Thu 25 + Fri 26 Mar 2010 Bloomsbury 4 Book now £470 £475
2007 Wed 31 + Thu 1 Mar 2010 Bloomsbury 5 Book now £470 £475
2007 Mon 12 + Tue 13 Apr 2010 Limehouse 5 Book now £470 £475
2003 Wed 14 + Thu 15 Apr 2010 Bloomsbury 9 Book now £345 £350
2007 Mon 19 + Tue 20 Apr 2010 Bloomsbury 4 Book now £470 £475
2007 Tue 27 + Wed 28 Apr 2010 Limehouse 7 Book now £445 £450
Full Schedule: See all 32 Project Intro Intermediate course dates.
Bookings currently available until 20th December 2010.

Gold
188 posts
replyReplyFri 4 May 2007, 14:44Trainer Garry said...

RE: resource splitting

When you assign or remove people from a task, Project lengthens or shortens the duration of the task based on the number of resources assigned to it, but it does not change the total work for the task. This is called effort-driven scheduling and is the default Microsoft Project uses when you assign resources to tasks.

As resources are added to a task, the total work on the task stays the same. The amount of work distributed to the resources assigned to the task, however, changes.

Effort-driven scheduling only takes effect when resources are added to or removed from a task. Effort-driven calculation rules are not applied when you change work, duration, and unit values for resources already assigned to a task.

When working with effort-driven scheduling, keep the following in mind:

The effort-driven calculations apply only after the first resource is assigned to the task. After a resource is assigned, the work value doesn't change as new resources are assigned to or removed from the same task.
The effort-driven calculations aren't applied to multiple resources that are assigned at the same time and that are the first assignments on a task. After this initial assignment of multiple resources, however, the work value doesn't change as new resources are assigned to or removed from the same task.
If the assigned task type is Fixed Units, assigning additional resources shortens the duration of the task. Learn more about task types.
If the assigned task type is Fixed Duration, assigning additional resources decreases the individual unit values for resources.
If the assigned task type is Fixed Work, assigning additional resources shortens the duration of the task.
Summary tasks and inserted projects cannot be set to effort-driven.


Related articles

· Why Very Small Businesses Benefit from Microsoft Project Training Seminars
· Problem Solve On The Job With MS Project
· Hadrian's Wall Scheduled With Office Project
· Keep Control Of Your Budget With MS Project
· MS Project: Project Manage your way to becoming a Home Owner

Ms project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips


Rate this page:
2.1/5 (108 votes cast)
Institute of IT Training - Accredited Training Provider ILM
Microsoft Certified Partner
Microsoft Office Specialist Authorised Testing Centre (MOS and MCAS)

Prodigy Platinum Learning Partner

Institute of IT Training - Accredited Training Provider
McAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Association of Computer Trainers verified by visa, mastercard securecard